The Raising of an Hotel – Timeline in Santa Fe de Veraguas

Take a look at our construction process in Santa Fe, Veraguas – Reminiscing!

My computer hard drive, recently failed, and a side benefit of transferring files to a new computer (because, hey, you just gotta look at the bright side when your computer starts to make gurgling sounds and awkward beeps), I got to take a look at some of the old photos from construction of our B&B over the past year. Hope you enjoy!

For those who don’t know, my husband oversaw construction. Our wedding anniversary is coming up (almost 10 years!), and looking at the time series of pics made me feel all warm, and appreciative of him.

Pre Construction - January
January, Pre-Construction

 

Construction Santa Fe, Panama February
February – Foundation

 

Construction in March, Coffee Mountain Inn
March Foundation

 

Construction, Santa Fe April
April – Walls & Electrical

 

Construction in May, Coffee Mountain Inn
May – Roof, Welding and More Electrical & Plumbing
Construction Santa Fe, Panama June
June – Roof, Indoor Plastering and Finishing of Walls, Leveling of Floors

 

Construction Santa Fe, Veraguas July
July – Outdoor Wall Stuccoing, Doors, Windows, and Tiles

 

Construction, Coffee Mountain Inn Santa Fe, Panama - August
August – Painting, Indoor Fixtures, Landscaping

 

Hotel Coffee Mountain Inn - Sept
September – Continued Landscaping

 

Hotel Coffee Mountain Inn, Panama October
October – Plants grow.

 

Hotel Santa Fe, Coffee Mountain Inn Panama - November
November – Plants grow – take a look at the passion fruit!

 

Hotel Coffee Mountain Inn - November
November – Front